Prepare a heat pump yourself

Preparing a heat pump or heat pump water heater yourself is perfectly possible: you have the appliance delivered into the room, prepare the pipes, the power supply and the condensate drain up to the spot, and make the base. The complete installation of the appliance is done by an installation company: us, from A to Z. That includes placing or hanging it, followed by connecting, pressurising, testing and commissioning. With our installation invoice you apply for ISDE; RVO decides on your application. Choose below which appliance you are preparing for; you then see, step by step, what you do yourself, where you stop, and what it costs you if you do not.

Which appliance?

Why preparing it yourself makes sense

There are too few installers, and with the switch from gas to heat pumps that is more likely to get worse than better in the coming years. Long waiting times and high hourly rates are the result. Most of the work on a heat pump is not skilled work: laying pipes, running a cable and making a base are things you can do well yourself. Then a professional only needs to come for the installation itself: placing the appliance, connecting it and commissioning it. With us that is one appointment of about two hours, bookable from 48 hours ahead.

First: do you want the ISDE grant?

Yes, I want the grant

Follow steps 1 to 5 and stop there. Do not connect anything, do not fill anything, do not switch anything on, and leave placing or hanging the appliance to us. RVO requires an installation company to install the heat pump. We do that, from A to Z, with the ISDE package for €349 (heat pump water heater €279), with an installation invoice for your application. Placing or hanging the appliance comes on top, in consultation, € 90.00 per hour, per started quarter of an hour.

No, no grant

With a monobloc you may then finish it yourself, on your own responsibility and following the manufacturer’s manual. Have it checked afterwards with our safety inspection for €99. But first read what you leave on the table.

What it costs if you finish it yourself

If you finish it yourself, you get no ISDE. With our ISDE package you do.

An example using the amount RVO itself mentions:

ISDE for a 4 kW heat pump with an A+++ label€2,125
VoltLogic ISDE package− €349
Missed saving if you finish it yourself€1,776
RVO example (2026). The amount depends on type and capacity; RVO decides on your application.

For a heat pump water heater RVO mentions its own amount, which depends on the type. With our ISDE package for €279 you keep most of it. RVO decides on your application.

Calculate it for your appliance:

Appliance bought or ordered
You keep± € 1,776Installing it yourself yields € 0 grant: RVO requires an installation company.
Estimated grant heat pump€ 2,125
ISDE package VoltLogic− € 349

An indication based on the RVO amounts for 2026. The amounts for 2027 are proposed by RVO and not final yet. No rights can be derived from this. RVO determines the amount and decides on your application. The exact amount per appliance is in the RVO meldcode lists; the conditions are on the ISDE page. Our price includes VAT and call-out costs within the radius; any travel costs or additional work come on top.

Compare with your quote

Do you have a quote for a complete installation? With a complete installation, a large part of the grant goes to installation costs. Enter your own amounts and see what you keep if you prepare it yourself.

An indication with your own amounts, not advice. Your own time for the preparatory work is not counted here. RVO decides on your grant.

Who does what

Diagram of an outdoor unit with anti-freeze valves, pipes through the facade, two 3-way valves with bypass, isolator switch and fuse box. Green numbers you do yourself, yellow numbers we do.
  • You (green): 1 base ready and the unit delivered next to the spot · 2 anti-freeze valves at the unit · 3 pipes through the facade, insulated outdoors · 4 two 3-way valves with bypass, indoors · 5 cable up to and including the isolator switch · 6 condensate drain · 9 dedicated circuit in the fuse box
  • We (yellow): 1 place or hang the unit, level and on anti-vibration mounts · 7 connect the anti-freeze valves to the unit with flexible hoses · 8 connect from the isolator switch to the unit. We check your circuit, RCD and fuse, then pressurising, venting, pressure and leak test, infrared check and commissioning.
Heat pump water heater with two 3-way valves and bypass. Cold water through 3-way valve 1, the inlet combination and the water heater; hot water through 3-way valve 2 to the taps. Green you do yourself, yellow we do.
  • You (green): 1 3-way valve on the cold water supply · 2 3-way valve on the hot water pipe to your taps · 3 the bypass between them, as short as possible · 6 the spot ready and the water heater delivered into the room. Set the valves to bypass and you keep hot water until we come.
  • We (yellow): 6 place or hang the water heater · 4 the inlet combination between the cold water valve and the water heater (pre-assembled at our workshop, tightened on site with a torque wrench) · 5 the connection of the water heater to the hot water valve. The inlet combination is charged as material; it is listed separately on your invoice.

Step 1. Choose your heat pump

  • Monobloc. The refrigerant is sealed in the factory inside the outdoor unit; only water goes inside. Nobody needs to work on the refrigerant. This is the type we install, as a heat pump or as a hybrid next to your gas boiler.
  • Heat pump water heater. Only makes hot tap water and is installed indoors. We install those too.
  • Hydrosplit. Here too the refrigerant stays in the outdoor unit and water runs inside. Not sure whether your model is possible? Email us the brand and model before you buy.
  • No split. With a split, refrigerant pipes run between indoors and outdoors. Only someone with an F-gas certificate may lay and fill them, not the buyer either. And since 2026, split air-to-water heat pumps with less than 3 kg of refrigerant no longer get ISDE.
  • For the grant: buy new, preferably from the RVO meldcode list, a home built before 2019, and keep the purchase invoice and proof of payment.

Step 2. Choose the location

  • Space around it. Keep to the clearances in the installation manual, for airflow and maintenance. Not tucked into a corner or under a low canopy: the unit then sucks its own cold air back in.
  • Noise. At the property boundary a heat pump may not produce more than 40 dB(A). Check the sound power in the documentation, do not choose a spot right under the neighbours’ bedroom window and not in a corner that reflects the sound.
  • Permit. Behind the house an outdoor unit usually needs no permit. At the front, on a listed building or in a protected townscape a permit may be needed. Check the Omgevingsloket.
  • Short route inside. The shorter the pipes between outdoor unit and home, the less heat loss and work.
  • Indoors. A heat pump water heater or indoor unit needs a solid floor or wall, space for maintenance and a drain nearby. A heat pump water heater often needs a minimum room volume or an air duct: see the manual.
  • Weight. When filled, a 200 to 300 litre heat pump water heater easily weighs 250 to 400 kg. Choose a solid, level floor.
  • Air. The water heater takes its heat from the air. Keep to the minimum room volume from the manual (often around 20 m³) or connect air ducts as the manual prescribes. In a room that is too small it cools the room down and works poorly.
  • Frost-free and accessible. In a frost-free room, with space for maintenance at the top and the front, and a drain nearby for the condensate and the overflow.

Step 3. Base ready, unit delivered (1)

  • Make the base according to the manual: tiles, concrete footings or a flat concrete slab, or a solid wall for wall brackets. Fit wall brackets only in consultation with us; we check them on the photos and correct them where needed.
  • Make sure the unit ends up at least 10 to 20 cm above the ground, so snow, leaves and ice from the condensate do not block the unit.
  • The complete installation of the appliance is done by an installation company: us, from A to Z. That includes placing or hanging it: we set the unit level, firmly fixed and on anti-vibration mounts, so no noise travels into your wall or floor. We do that in consultation, € 90.00 per hour, per started quarter of an hour.
  • Have the unit delivered next to the spot; still packed is fine. An outdoor unit often weighs 60 to 150 kg and must stay upright.

Step 3. Spot ready, water heater delivered (6)

  • A solid, level floor with the clearances stated in the manual, or a sturdy wall for a wall-hung model. Fit a wall bracket only in consultation with us; we check it on the photos and correct it where needed.
  • Have it transported upright and delivered into the room, next to the spot; still packed is fine. If it has been lying down anyway, let it stand upright for a while before it is switched on; how long is in the manual.
  • Choose a spot close to the cold and hot water pipes and to a drain, so the pipes stay short. We place or hang it, level and firmly fixed, in consultation, € 90.00 per hour, per started quarter of an hour.

Step 4. 3-way valves, pipes and anti-freeze valves (2, 3 and 4)

  • Indoors, just behind the facade, fit a 3-way ball valve in the flow and in the return, with a bypass between them that is as short as possible (4). Set them to bypass. How that works is explained below.
  • From the 3-way valves, lay the flow and return pipes through the facade to the spot of the unit (3), in the diameter from the manual and in the unit’s connection size. We do not fit reducers.
  • Let them end outdoors in two anti-freeze valves (2), 30 to 50 cm from the unit’s water connections, side by side at the same height, at the lowest point and at least 20 cm above the ground. Put “flow” and “return” labels on them. If the power fails during frost, the valves drain the outdoor section. Using glycol (see Frost protection)? Then let the pipes end at the same place in two shut-off valves instead of anti-freeze valves.
  • Marking is mandatory. Clearly mark every pipe at the anti-freeze valves and the 3-way valves with a label or coloured tape: flow (red) and return (blue), and for a heat pump water heater hot (red) and cold (blue). If the marking is missing or wrong, we have to trace the pipes; we charge that time as additional work.
  • Filled, under pressure and leak-free. Your own pipework is already filled and at system pressure before the appointment, with the 3-way valves set to bypass, and does not leak. That way you test your own work days in advance. We fill the section from the 3-way valves to the outside.
  • Flushed and clean. New pipes have been flushed, free of solder residue, swarf or other dirt, with a dirt or magnetite filter if the manual prescribes one. Dirt in the system is your responsibility.
  • Frost protection. You arrange it, in one of two ways: anti-freeze valves at the unit, or the whole installation filled with glycol, if the manufacturer allows it. With glycol: use propylene glycol, ready-mixed at the percentage from the manual (top up with the same mix, never with tap water), and fit no anti-freeze valves: during frost they would drain your glycol. With an open manifold or a buffer tank without a heat exchanger, the glycol is in the whole installation. State the product and percentage in your preparation; we measure it at handover and note it on the handover report. If frost protection is missing, we note it on the handover report and damage from freezing is at your risk.
  • Insulate the pipes outdoors up to the anti-freeze valves, with insulation that withstands sunlight and moisture. Pipes through the wall in a sleeve, with the opening properly sealed.
  • Buffer tank, expansion vessel, dirt filter and the connection to underfloor heating or radiators: follow the manufacturer’s manual, or have an installer of your choice do it. That pipework is yours; we do not modify it.

Step 4. Two 3-way valves on cold and hot (1, 2 and 3)

  • Fit a 3-way ball valve on the cold water supply (1) and one on the hot water pipe to your taps (2), with a bypass between them that is as short as possible (3). Set them to bypass and you keep hot water until we come. How that works is explained below.
  • Lay the pipes to the water heater in the diameter from the manual and in the water heater’s connection size. We do not fit reducers.
  • Marking is mandatory. Clearly mark the pipes at the 3-way valves: hot (red) and cold (blue). If the marking is missing or wrong, we have to trace the pipes; we charge that time as additional work.
  • We fit the inlet combination (4), between the cold water valve and the water heater, and also the connection to the hot water valve (5). The inlet combination is charged as material; it is listed separately on your invoice.
  • Do not insulate the hot water pipe to your taps: an insulated pipe stays lukewarm for a long time, and that is exactly what legionella likes. A heat pump water heater indoors does not need anti-freeze valves.

Two 3-way valves: the bypass

For every heat pump and heat pump water heater we work with the same set: two 3-way ball valves with a short piece of pipe between them, the bypass. Fewer couplings than separate valves and tees, so less chance of leaks and fewer mistakes.

Two 3-way valves with bypass. A: on bypass, the appliance is shut off on both sides. B: in operation, the water flows through the appliance and the bypass is shut off on both sides.
A: bypass. The water of your home flows through the bypass; the appliance is shut off on both sides (black = closed). B: in operation. The water flows through the appliance; the bypass is shut off on both sides.
  • Until the appointment: bypass (A). Your heating or hot water works as always, and you can already fill your own pipework and put it under pressure.
  • After our installation: in operation (B). We switch over after pressurising, venting and the pressure and leak test. The bypass is then shut off on both sides, so no stagnant piece of pipe stays attached to your installation, which helps against legionella.
  • Maintenance or a fault: bypass again (A). The appliance is then shut off on both sides and can be disconnected without draining your home. For a heat pump water heater: after switching back, let the hot taps run for a while.
  • Hybrid heat pump: the 3-way valves sit in the pipe the manual prescribes, usually the return before your boiler. Check the installation manual for the diagram your brand prescribes.

Step 5. Cable, isolator switch and condensate drain (5, 6 and 9)

  • Connect a dedicated circuit in the fuse box, with a circuit breaker behind an RCD or an RCBO, as the manual prescribes, and run the cable in the size from the manual to the isolator switch. Leave the circuit switched off until we come.
  • Fit a double-pole isolator switch within 1 metre of the spot of the unit, clearly visible and accessible, and connect the cable to the input of the switch. We do the section from the switch to the unit; leave about 50 cm of cable at the unit.
  • Lay a condensate drain up to directly below or next to where the unit’s condensate connection will be, with a fall, and frost-free where possible.
  • What you need: 3-way valves, an isolator switch, cable glands, condensate hose and labels; all dimensions are on Preparation requirements. A complete preparation kit is coming soon at Ampflow Energy.

Step 5. Power and drain

  • Heat pump water heater with a plug (such as the Ariston Lydos)? Then an earthed socket within reach of the plug is enough, without an isolator switch. We still recommend a dedicated circuit. Two water heaters with plugs in cascade (for example two Lydos units) may share one circuit, if the manual allows it.
  • Fixed connection without a plug? Then a dedicated circuit in the fuse box with an isolator switch at the water heater, as the manual prescribes. Leave the circuit switched off until we come.
  • Lay a drain with a trap or funnel for the condensate and for the overflow of the inlet combination, close to the water heater and with a fall.
  • What you need: two 3-way valves, condensate hose and labels; all dimensions are on Preparation requirements.

Want the grant? Stop here.

Leave the appliance as it was delivered: placing or hanging it is our job. Do not connect anything to the unit: no connection from the isolator switch to the unit and no water connection. Leave the circuit switched off, do not fill the system and do not switch anything on. Book your appointment and send us photos of your preparation. Anything else you prepare yourself, we agree together based on those photos (in consultation). If it cannot be done for the fixed price, you get a full refund.

Checklist

These items are there for your installation: so it is safe, works well and lasts a long time. If everything is ticked off, we are done quickly at the appointment. Your ticks are kept on this device. Booked? Then tick off on your personal page (link in your confirmation): that one counts for your appointment.

What we do next, from A to Z

We place or hang the appliance in its final position, level and firmly fixed (an outdoor unit on anti-vibration mounts), checking your base and any wall bracket as we go. Placing or hanging is charged in consultation, € 90.00 per hour, per started quarter of an hour. We check your circuit, RCD and fuse. Then we make the electrical connection from the isolator switch to the unit and the hydraulic connections on the unit, pressurise and vent, carry out a pressure and leak test and an infrared check, and commission the heat pump according to the manufacturer’s instructions. You get an explanation of the controls, a handover report and the installation invoice for your ISDE application. That invoice only states what we did.

Without a grant: finishing it yourself

If you do not want ISDE, you may connect and commission a monobloc yourself. That is your choice and your responsibility. Please note:

  • You leave the grant on the table, see the example above.
  • Warranty. Some manufacturers only give full warranty if an installer commissions or registers the heat pump. Read the warranty terms before you start.
  • Safety. The electrical installation must comply with NEN 1010. If in doubt, do not do it yourself.
  • Have it checked. With our safety inspection (€99) we check the placement, electrics, water side and operation, and you get a report. An inspection is not an installation and does not qualify for ISDE.

Common mistakes

  • Spot too close to the wall or in a corner. Worse performance and more noise. Keep to the clearances in the manual.
  • No 3-way valves with bypass. Then your whole system has to be drained for every connection or fault, and you are without heating or hot water until we come.
  • Anti-freeze valves before the 3-way valves or high up in the pipe. They belong outdoors, close to the unit, at the lowest point. Otherwise they cannot drain the outdoor section.
  • Outdoor pipes not or poorly insulated. Heat loss and a risk of freezing.
  • Pipes or cable too thin. Check the manual, not whatever happens to be lying around.
  • Already placed, connected or filled yourself anyway. If you want the grant, leave the complete installation, including placing or hanging, to an installation company. So really stop after step 5.
  • No 3-way valves with bypass. Then you are without hot water during a fault or maintenance, and the water heater has to be drained to disconnect it.
  • A shut-off valve between the inlet combination and the water heater. That is not allowed: the safety device could then be shut off. That is why we fit the inlet combination.
  • Room too small or no air duct. The water heater cools the room down and works poorly. Keep to the manual.
  • Hot water pipe insulated. Stays lukewarm for a long time; that helps legionella.
  • Already placed, connected or filled yourself anyway. If you want the grant, leave the complete installation, including placing or hanging, to an installation company. So really stop after step 5.

After installation

  • Keep the outdoor unit clear of leaves, snow and plants.
  • Check the water pressure now and then and clean the dirt filter according to the manual.
  • Have the installation checked regularly; some manufacturers require this for the warranty.
  • Keep the air inlet and the filter of the water heater clean according to the manual.
  • Leave the legionella programme switched on.
  • Briefly open the overflow of the inlet combination once a year, by turning or pressing it, so it does not seize up.
  • Have the installation checked regularly; some manufacturers require this for the warranty.

Questions

May I install a heat pump myself?

Without a grant, as a private individual you may place and connect a monobloc yourself. If you want the ISDE grant, the complete installation of the appliance is done by an installation company: us, from A to Z. That includes placing or hanging it, followed by connecting, pressurising, testing and commissioning. You may still prepare it yourself: having the appliance delivered into the room, and preparing the pipes, power supply, condensate drain and base up to the spot.

Do I get a grant if I do the preparation myself?

We then do the complete installation, including placing or hanging the appliance, and you get our installation invoice with brand, model, meldcode, serial number, address and installation date. RVO assesses your application and also decides whether preparation you did yourself counts; nobody can guarantee a grant. Not sure what you may prepare yourself? We agree that together in advance, based on the photos of your preparation.

How soon can you come?

You book a time in the calendar yourself, from 48 hours ahead. You see straight away which days and times are available. Your date is then provisional; at the latest 48 hours beforehand your checklist must be complete, with photos.

I have a hydrosplit. Can you install it?

Often yes, because the refrigerant stays in the outdoor unit. Email us the brand and model and we will let you know before you book.

Can I lay a split heat pump myself?

No. Laying refrigerant pipes, pulling a vacuum and filling may only be done by an F-gas certified company. That is why we only work on monoblocs and heat pump water heaters.